Bond 2016

GPISD Looking Forward to the Future

The Galena Park Independent School District has advanced to the design phase of the first four projects of the 2016 voter-approved $290 million bond. The schematic design on the first four campuses to be rebuilt by the bond passed board approval at the December 12, 2016 meeting. The architects will move on to the design phase.

 

First Four Projects:

Step I
Select Professional Services
completed - Fall 2016

Step II
Schematic Design Development
completed - Fall 2016

Step III
Design Development
in progress

Step IV
Construction - Summer 2017

 

Galena Park Elementary

Galena Park Elementary
Address: 401 North Main
Original Opening: 1936
Capacity: 700 Students
Architect: PBK Architects

More Details

 

 

North Shore Elementary

North Shore Elementary
Address: 14310 Duncannon
Original Opening: 1961
Capacity: 1025 Students
Architect: Huckabee Architects

More Details

 

Woodland Acres Elementary

Woodland Acres Elementary
Address: 12936 Sarah's Lane
Original Opening: 1954
Capacity: 500 Students
Architect: Smith & Co. Architects in association with Pfluger Architects

More Details

 

North Shore Senior High 10th Grade Campus

North Shore Senior High 10th Grade
Address:
Original Opening: New Construction
Capacity: 1200 Students
Architect: Madeline Chu Architects

More Details

 

 

 

On behalf of the children of Galena Park ISD, THANK YOU!

Bond News

Galena Park ISD Community Approves $290 Million Bond Package. Read more